Sno | District/Division | Transformer Name | Capacity (kVA) |
Urban/Rural | Remarks | Damage Date and Time |
---|---|---|---|---|---|---|
1 | Bandipora | Imambarah Dangerpora | 100 | Rural | 24-Dec-2024 07:05:00 | |
2 | Bandipora | 250 kva panchayat Naidkhai | 250 | Rural | Process for arranging and lifting the DT initiated | 09-Jan-2025 22:00:00 |
3 | Bandipora | Khawaja mohalla Naidkhai 100 kv | 100 | Rural | Process for arranging and lifting the DT initiated | 11-Jan-2025 22:50:00 |
4 | Bandipora | Muqdam mohallah kunon | 63 | Rural | Single phase | 07-Mar-2025 22:27:00 |
5 | Bandipora | Muqdam mohallah kunon | 63 | Rural | Single phase | 07-Mar-2025 22:27:00 |
6 | Bandipora | Muqdam mohallah kunon | 63 | Rural | Single phase | 07-Mar-2025 22:27:00 |
7 | Bandipora | Muqdam mohallah kunon | 63 | Rural | Single phase | 07-Mar-2025 22:27:00 |
8 | Bandipora | Muqdam mohallah kunon | 63 | Rural | Single phase | 07-Mar-2025 22:27:00 |
9 | Bandipora | Muqdam mohallah kunon | 63 | Rural | Single phase | 07-Mar-2025 22:27:00 |
10 | Bandipora | Muqdam mohallah kunon | 63 | Rural | Single phase | 07-Mar-2025 22:27:00 |
11 | Bandipora | Kath mohalla hakbara | 100 | Rural | Lifted | 21-Mar-2025 11:30:00 |